05.06.2020
Dynamics of construction as of MAY
1 turn
House №1
100% completed works on the following works:
• Construction of a monolithic frame of the house;
• Laying of walls and partitions;
• Waterproofing of a socle;
• Roof installation;
• Installation of water supply on all floors;
• Heating installation. All floors;
• Installation of power supply system on all floors;
• Pouring cement-sand screed. All floors;
• Insulation and painting of the facade;
• Arrangement of translucent structures of the 1st floor;
• Installation of doors;
• Internal plastering works on all floors;
• Glazing. All floors.
95% or more of work performed with:
• Lightning protection;
• Installation of sewerage.
85-90% are ready to work with:
• Soil backfill to the design mark;
• Finishing of MOS 2-24 floors;
• Installation of individual heating points;
• Installation of a ventilated facade of the plinth;
• Installation of elevators.
60% finished work with:
• Installation of radiators;
• Installation of fire alarm and smoke removal.
At 15% readiness:
• Finishing the design lobby on the 1st floor.
House №2
The following works are 100% completed:
• Erection of a monolithic framework;
• Laying of walls and partitions on all floors;
• Waterproofing of a socle;
• Installation of water supply system;
• Installation of a heating system;
• Arrangement of the power supply system;
• Filling of cement-sand screed;
• Internal plastering works on all floors;
• Glazing on all floors.
At the stage of 80-90% readiness the following works:
• Filling of soil to a design mark;
• Roof installation;
• Installation of elevators;
• Facade insulation.
At the stage of 25% readiness:
• Facade painting works.
House №3
To date, the following works have been completed:
• Erection of a monolithic framework;
• Laying of walls and partitions;
• Glazing on all floors;
• Roof installation;
• Pouring cement-sand screed;
• Insulation and painting of the facade;
• Plastering works on all floors;
• Installation of doors on all floors;
• Installation of translucent structures on the 1st floor;
• Installation of an individual heating point;
• Works on the arrangement of engineering networks, namely:
- Lightning protection;
- Sewerage;
- Water supply;
- Heating;
- Power supply.
80-90% are ready to work with:
• Soil backfill to the design mark;
• Installation of radiators;
• Installation of elevators;
• Decoration of common areas on the 2nd-26th floor;
• Installation of a ventilated facade of the plinth.
70% readiness
• Installation of fire safety and smoke removal system.
At the stage of 15% readiness:
• Decoration of the design lobby on the 1st floor.
2 turns
House №4
Completed 100% of works with:
• Pouring the pit;
• Testing of pile bushes;
• Testing of 326 piles;
• Installation of the tower crane foundation;
• Arrangement of the foundation;
• Monolithic frame to the 3rd floor.
75% ready:
• Monolithic frame of the 4th floor.
House №5
The following works have been completed:
• Filling the pit;
• Testing of pile bushes;
• Testing of 327 piles;
• Installation of the tower crane foundation.
House №6
100% ready from:
• Pouring the pit;
• Testing of pile bushes;
• Testing of 327 piles;
• Monolithic frame of the basement and the 1st floor.
50% finished works:
• Arrangement of the foundation.
Sincerely,
your Light Park