    https://youtu.be/_XsSkjhwjN4 House 1 Completed works with: • roof arrangement; • Plastering of floors and staircase # 1; In the final stage - 90-95% readiness: • arrangement of the ventilated plinth facade; • Installation of elevators and doors • grounding to the design mark Work continues on: • decoration of public places; • installation of individual heat point; • stucco of staircase # 2; • Installation of external engineering networks: water supply and sewerage. House 2 Completed works with: • installation of cement-sand screed; • heating up to 24 floors; • installation of water supply to the 24th floor; • power supply up to the 20th floor; • waterproofing of a socle. Work continues on: • installation of elevators; • roof installation; • facade insulation. House 3 Work is underway on: • installation of a ventilated facade of the plinth; • assemblies of individual heating point; • decoration of common areas; • installation of elevators. • installation of external engineering networks: water supply and sewerage. Completed works with: • installation of translucent structures on the 1st floor; • roof arrangement. House 4 Completed works on the arrangement of the basement (pantry, wheelchair); Work is being done to fill the monolithic frame of the 1st floor. House 5 Field pavement works completed (327 piles). House 6 Work is in progress to fill the monolithic frame of the basement. Field pavement works completed (327 piles). Sincerely, Svitlo Park
    Hide article