  • February Dynamics Of Construction

    Friends, meet the video report from the construction site for February https://svitlopark.ua/about/construction/

    First turn:
    houses №1, №2, №3 were built.

    Another queue:

    4th house:
    the construction of the monolithic frame has been completed.
    Waterproofing works have been finalized.
    Installation of walls of 2-6 and 8-9 floors is finished.
    80% of the walls of 7 and 10-15 floors are ready.
    Stage 30% readiness - laying the walls of the 16th floor.
    Completed work on the masonry of basement partitions and 2-8 floors.
    At 40% readiness - laying partitions of 10-13 floors.
    At the stage of 50% readiness - installation of sewerage 2-8 floors.

    5th house:
    at the stage of 100% readiness - installation of a monolithic frame of 1-13 floors.
    Waterproofing works have been completed.
    Work is underway to install the walls - currently 100 and 3 floors are 100% ready.

    6th house:
    completed work on the installation of a monolithic frame of 0-18 floors.
    70% readiness of a monolith of 19-20 floors.
    50% readiness - a monolith of 21-23 floors.
    Waterproofing works have been finalized.
    Work on the installation of partitions in the basement and on 2-4 floors has been completed.
    At 30% readiness - partitions of 6-7 floors.
    Work on the arrangement of the walls continues:
    - at the stage of 80% readiness - work on 2-8 floors;
    - 50% of the walls of the 9th-12th floors are ready.

    Parking:
    arranged grilles.
    70% of the construction of vertical parking structures has been completed.
    Work is underway to install a power plate.

    The third stage of construction:
    in buildings №7 and №8 the work on the construction of the pit and experimental pile bushes was completed, as well as the testing phase of piles was completed.